• EN
  • Project profile

    Aratinga Thermal Power Plant (Biomass)

    O&M

    Iqony Solutions do Brasil was hired by ERB to perform the following services: support in plant acceptance, support in commissioning, training, O&M support.

    The plant consists of a cogeneration project of 150 tons/hour of steam and 17 MWe of generation. The plant includes a biomass processing unit, fluidized bed boiler with ESP. The plant is installed within the DOW chemical complex providing it with necessary utilities: energy and process steam.

    Installed capacity17 MWe + 150 tons/h
    CommissioningJanuary 2014 - July 2014 (COD)
    CustomerERB - Energia Renováveis do Brasil
    Execution of SES services2013 - 2015